Start of Installation in Barwice
In Barwice started the installation phase of the 42 MW windfarm. The first tower segments of the 14 turbines, which have a hub height of 115 m, have been erected last week. The installation of the other main components goes on step by step with a special 120 m high crane. WiNRG accompanies the installation and will take over the commercial management of the wind park after grid connection.